Shenandoah Valley Infrastructure Replacement Project

 

Project Background

 

The Shenandoah Valley Infrastructure Project will replace and improve the water lines, sewer lines, storm drains and streets in the city's original residential subdivision. The project will cost an estimated $26.5 million dollars and will take four to five years to complete. In May 2007, voters overwhelmingly approved a $19.5 million bond program to help fund the project. The remaining costs will be funded by financing associated with the city's water and sewer utility system. 

   

Priority Area 3 is currently underway. The contractor, SER Construction, is working primarily in the Thornwood/Crestwood/Deadwood/Elmwood and Holly Hill region and will move north along Driftwood after that. 

 

The entire project is scheduled to be completed in late spring of 2012. 

 

Priority Area III Site Specific Map


Contact Information

 

City of Shenandoah
City Hall: (281) 298-5522

Steve Early
Utilities/Maintenance Supervisor
(832) 585-8149
email

 

Byron Bevers, P.E.
Director of Public Works
(832) 545-8142
email


Bleyl & Associates

Jerry Woodrome
Inspector
(936) 689-7833 

HDR/Claunch & Miller

Office: (713) 622-9264

Harry B. Walker
Vice President
(713) 425-0124

Steve Arnold
Construction Manager
(713) 425-0163


 

SER Construction Partners

Roman Trevino 
Project Representative
(713) 545-7635